Digging Footings & Electricity Hook Up

Digging Footings, Connecting Electricity, taking delivery of equipment

A temporary electricity meter was connected in order to provide power during the initial build phase.  The electricity company charges double the standard rate for electricity from this type of meter.  It will be replaced with standard meter once a circuit breaker box and wiring has been installed in the semi-finished house.

Also today, work began on digging the holes for the foundations and we took delivery of the equipment and materials that will be required over the coming days.